1000 Terminal Dr, Macon, GA 31297
Spincasting
8 Weeks
Our team provided all necessary materials, equipment, labor, and supervision to restore the structural integrity of 1,950 linear feet of an existing 120-inch storm drain pipe located beneath Runway 5. This project was a key component of the broader airport and runway upgrade, which includes extending the runway to accommodate larger aircraft. We successfully completed our scope of work within an 8-week timeframe, ensuring efficiency and adherence to project requirements. To accomplish this, we collaborated Piedmont Mining LLC and HK Solutions.